![]() Also, notice that the new 30d Duration for Activity 55 did not roll-up. However, after adjusting the OD to 30d we can see that Remaining Duration and At Complete Duration stayed at 10d and the dates still reflect a 10d Duration as well. As seen in the example Activity 55 OD / At Complete Duration / RD are the same at 10d. No Durations have been changed yet in this example below. ![]() This first was noticed when the dates on the activity did not shift and the rolled-up OD for a phase did not reflect the new OD that was just entered. Even though the Original Duration was changed for the activity, the At Completion Duration / RD was not. An issue came up while changing Original Durations. These projects were in the planning phase of the Project lifecycle and durations were still being changed on various activities. Recently Project schedules were imported into Primavera P6 from a client. DURATION ERROR IMPORTING MS PROJECT TO P6 MICROSOFT PROJECT AND ORACLE PRIMAVERA P6 DOWNLOAD THE PDF HERE